Civitech Stadia- Construction Update for Month of June 2017

Civitech Stadia- Construction Update for Month of June 2017

Construction Update, News, Recent Blogs 0 Comment

We sincerely thank you for choosing Civitech Stadia as your dream home. It gives us sense of satisfaction that we are meeting your expectations and reaching our promises made to you. We are glad to provide you the construction update for month of June 2017

Herewith we are providing the updated construction pictures and presentation of construction images.

Tower A:

  • Brick-Work has been completed
  • Balcony railing has been completed
  • Internal door frame has been completed
  • Electrical work has been completed
  • Plumbing work(internal CPVC) has been completed
  • Internal plaster has been completed
  • External Plaster has been completed

Tower B:

  • Brick-Work has been completed
  • Balcony railing has been completed
  • Internal door frame work has been completed
  • Electrical work has been completed
  • Plumbing work(internal CPVC) has been completed
  • Internal plaster has been completed
  • External Plaster has been completed upto 95%

Tower C:

  • Brick-Work has been completed
  • Balcony railing has been completed
  • Internal door frame work has been completed
  • Electrical work has been completed
  • Plumbing work(internal CPVC) has been completed
  • Internal plaster has been completed
  • External Plaster has been completed upto 50%

Tower D:

  • Brick-Work has been completed
  • Balcony railing has been completed
  • Internal door frame has been completed
  • Electrical work has been completed
  • Plumbing work(internal CPVC) has been completed
  • Internal plaster has been completed upto 21st floor
  • External Plaster has been completed upto 65%

Tower E:

  • Brick-Work has been completed
  • Balcony railing has been completed
  • Internal door frame has been completed
  • Electrical work has been completed
  • Plumbing work(internal CPVC) has been completed
  • Internal plaster has been completed upto 11th floor
  • External Plaster has been completed upto 20%

Tower F:

  • Brick-Work has been completed
  • Balcony railing has been completed
  • Internal door frame has been completed
  • Electrical work has been completed
  • Plumbing work(internal CPVC) has been completed
  • Internal plaster is in progress
  • External Plaster is in progress


* Non Tower Area (Ramp, UG Tank, External road etc.) are also in progress